Friday 9 May 2014

Plaster & Stairs - WK 18

Week 18

Mon 05th May - Sun 11 May 2014


We had a slow run at the start of the week but they sure made up for it once the plaster and staris arrived.


Heres the work for the week:-
- Additional (2) evaporative ducts installed to ground floor
- Plaster and Cornices delivered
- Ground / First Floor Plaster installed
- Plaster Wall tape and joint
- Stairs Installed



Mon 05 May - Evaporative Ducts to Ground Floor - Day 85
The heating and cooling guys were back to install the additional (2) evaporative ducts to ground floor that were missed Week 12.

Also they fixed up the ducts issue I raised regarding the heating/cooling ducts coming apart

Heater Ducts on the Roof coming apart

With every hope plaster did not show up ::sad::   So I decided to give SS a call to see whats happening.
Funnily enough SS also thought that they were due to start last Thur/Fri. He told me he follow up.
Within 5 minutes SS called me back to advise that due to house being a double storey they needed special crains to get the plaster to first floor so truck is booked in for tommorrow.


Heres hope they will show up tomorrow 


Tue 06 May - Plaster & Cornices Delivered - Day 86
Delivery:  Plaster (Gyprock) delivered .. YAH!!!! :z: :z: :z:
My neigbour told me the trucks (with special crains) were there nice and early.

Here's is a photo of the plaster being passed through via the rumpus room window on the first floor using crains.. now thats cool..




Plaster and Cornices



Wed 07 May - Ground /First Floor Plastered - Day 87
Talk about make up for loss time, plasterer were there nice and early (7:30am) hammering away and by the time I rocked up after work they had completed ground and nearly done with first floor :z::z:

Weekly Contract Admin status update:-
Plaster is nearly complete and Stairs has been booked in for this Friday. Start of next week cabinetry will be delivered and installed.



Thu 08 May - Plaster Joints & Stair Delivery - Day 88
Delivery: Timber Staircase (Vic Ash) delivered
The plasterers (total of 5) were back nice and early and had finish tapping and jointing the plaster walls together. Think the only thing left for them to do is cornices???? or is there more to it???

Also the delivery of the Stair Timber pieces, YAH!!!! ..We certainly going to see stairs tomorrow :wink: :wink: So excited cant wait ... Was anyone else excited to see their stairs as I am??




Fri 09 May - Cabinetry, Doors  delivered & Stairs Done - Day 89
What a day it was today.. all i can say is today has been one of those days that all i can see is .... WOW !!!!!!

The stairs has finally been put in and it looks so amazing.. cant believe how the look of the stairs can make a very big difference to a home. I was really nervous to see this come up as it was one of my 2nd biggest upgrade for the home and it turned out just the way i wanted it ::celeb:: ::celeb::

Also our internal walls, architraves, and cabinetry were all delivered today. :: :: This was suppose to show up next Monday so early than expected.. but not complaining ::lol::

Ok i know you all dying to see some photos of this week


Front Entry Bulk heads


Kitchen Bulkhead


Plaster around the Alfresco Sliding doors  



Bathroom

cabinetry


Stairs to lower/ground level


Stairs to upper/first void area








Sun 11 May - Plaster Joints  - Day 89
Today the plasterer were back on sight nice and early (7:30am - 15:00pm) to finish off setting the joints in the plaster wall/ ceiling so they can make it appear seamless. Now we just need to see the cornice go in to make it look complete.


All I have to say for this week is WOW So happy for this weeks progress. It truly makes up for the last two weeks (between Easter/ANZAC break).
Am so looking forward to another busy and excited week ahead... Hopefully by this time next week I can show off my Kitchen Cabinets ::lol:: 