TIMELINE

TIMELINE

Presite

 26 June 2013 - Purchase LAND

02 Oct 2013 - Registration and paid $1000 to Burbank
10 Oct 2013 - Soil test and Site Survey requested
22 Oct 2013 - Signed our Tender and paid $2000 to Burbank

08 Nov2013  Bank Approval
12 Nov 2013 Water Meter installed
13 Nov 2013  Colour Appointment at Edge Studio
19 Nov 2013  More variations signed and sent back (Variation 4-6)
24 Nov 2013 Site Costing completed (Variation 8)
25 Nov 2013 Energy Rating Report

29 Nov 2013  Engineer Plan Completed

11 Dec 2013 - Permit approved
12 Dec 2013 - Final Construction drawing updated and signed (Version F)

13 Dec 2013 - Refer file to Construction Department
19 Dec 2013 - Received SS courtesy call to advise will be commencing construction start of 2014.

Construction /Onsite

Stage 1 SLAB
07 Jan 2014 (Week 1) Site Fence went up and port-a-loo delivered
09 Jan 2014 Sight Scrape
15 Jan 2014 (Week 2) 35 Concrete Piers
17 Jan 2014 Electric Meter Box Installed
20 Jan 2014 Sewage and Underground Pipes completed
22 Jan 2014 ( Week 3)SLAB preparation
23 Jan 2014 Slab Poured
28 Jan 2014 Invoice for first progress payment received (Slab payment)
29 Jan 2014 (Week 4) Received Burbank commencement letter


Stage 2 FRAME
03 Feb 2014 (Week 5) Frames delivered
05 Feb 2014 Ground Floor Frame assembled
10 Feb 2014 (Week 6) First Floor Frame put up
11 Feb 2014 Roof Trusses up
12 Feb 2014 Garage Roof Truss and Windows Installed
13 Feb 2014 Plumbing rough ins
14 Feb 2014 Invoice for Second progress payment received (Frame payment)


Stage 3 LOCK UP
18 Feb 2014 (Week 7) Ground Floor wrapped
19 Feb 2014 Bricks Delivered
20 Feb 2014 (Week 7 - 10) Brick Work to Ground Floor started

12 Mar 2014 (Week 9) Scaffold erected
14 Mar 2014 Fascia Installed
15 Mar 2014 Gutter Installed
17 Mar 2014 (Week 11) Roof Tiles delivered, First Floor Wrapped & Roof Scaffold erected
18 Mar 2014 Roof Batton
19 Mar 2014 Roof Tiles
24 Mar 2014 (Week 12 - 13)  First Floor Bricking Starts 
26 Mar 2014 Heating and Cooling Ducts installed
28 Mar 2014 Solar Hot Water Panel installed

03 Apr 2014 Bath Tub delivered
08 Apr 2014 (Week 14) Eletrical Rough ins
09 Apr 2014 Plaster prepartion / Wall Leveling
10 Apr 2014 Eave installed & Front face rendering commences
12 Apr 2014 Eave painted (first coat)
14 Apr 2014 (Week 15) Wall Installation batts delivered
15 Apr 2014 First Floor Bricks cleaned & wall installations started
16 Apr 2014 Received SS courtesy for Lock up , Invoice for Third progress payment received (Lock up payment)



Stage 4 FIXING 

16 Apr 2014 Wall installation completed
17 Apr 2014 Second undercoat of rendering
18- 25 Apr 2014 Easter/ANZAC holiday
20 Apr 2014 (Week 16) Downpipes installed
28 Apr 2014 (Week 17) First Floor windows cleaned
29 Apr 2014 More Electrical Rough ins (special request)
30 Apr 2014 Scaffold Down & Floor Sanding

06 May 2014 (Week 18) Plaster & cornices delivered, more undercoat rendering
07 May 2014 Ground / First Floor Plastered
08 May 2014 Stairs Delivered & Plaster Wall joints starts
09 May 2014 Internal doors , cabinetry delivered & Stairs IN
13 May 2014 (Week 19) Internal garage door hung. Officially locked out!!!!
14 May 2014 Kitchen, Butler Pantry and Laundry Cabinets installed, plaster wall joints done
16 May 2014 Sight Clean
20 May 2014  (Week 20) Shower Recess Waterproofing
21 May 2014 Cornices installed
23 May 2014 Front Door Delivered
26 May 2014 (Week 21) Vanity/Kitchen Sink & Caesarstone Bench delivered and installed
27 May 2014 Ground Floor Bricks cleaned, architraves continues
28 May 2014 Internal Door Hung
29 May 2014 Ground Floor Skirting start
30 May 2014 Ground Floor architraves/Skirting (complete)

02 Jun 2014 (Week 22) Garage Fascia and Gutter delivered and installed
04 Jun 2014  Garage Scaffold erected
05 Jun 2014 Garage Roof Tiled, Vanity Caesarstone Bench installed.
06 Jun 2014 Garage Subfloor
12 Jun 2014 (Week 23) Garage Face Rendering
13 Jun 2014 Garage internal ceiling and wall plastered, Received SS courtesy for Fixing , Invoice for Fourth progress payment received (Fixing payment)

 

Stage 5 Final inspection (PCI)
16 Jun 2014 (Week 24) Glass splash-back installed, paint preparation
18 Jun 2014 Wet area Waterproofing
19 Jun 2014 Full Face Rendering
23 Jun 2014 (Week 25) Fixing Walk-through, Painting commences
26 Jun 2014 Downpipe connected to stormwater system
30 June 2014 (Week 26) Wall and Floor Tiles delivered

03 Jul 2014 First Floor Floor and Balcony Tiled
04 Jul 2014 Garage Panel Door installed/ Ground Floor Tiled


10 Jul 2014 (Week 27) Electrical Light Fittings (First Floor)
11 Jul 2014 Plumbing Taps Fittings
14 Jul 2014 (Week 28) Heating & Cooling Vents Fittings
15 Jul 2014 Toilets, Mirror robes, Shower screen & mirrors 
16 Jul 2014 Carpet Underlay/House Cleaned, Admin called to advise issue with Shower Heads
17 Jul 2014 Carpet Laid/ Security and Intercom system installed
18 Jul 2014 First floor electrical work (Electrical wall plates)/Fly Screen installed
19 Jul 2014 Internal Door Handles, Bathroom fittings
21 Jul 2014 (Week 29) Sight Clean, Ground floor electrical work (Electrical wall plates)
22 Jul 2014 Site Fence , sight cage and port-a-loo removed
24 Jul 2014 Water Meter / Telephone Line Trenching
25 Jul 2014 Front Door/ Stair Painted
28 Jul 2014 (Week 30) Kitchen Island Pendant light installed
30 Jul 2014 Gas Meter installed

01 Aug 2014 Internal Garage Wall painted
04 Aug 2014 (Week 31) Crack Master Mirror Robes replaced
11 Aug 2014 (Week 32) Still awaiting PCI to be booked
21 Aug 2014 (Week 33) Outstanding issue fixed
22 Aug 2014 PCI booked
26 Aug 2014 (Week 34) House cleaned, Invoice for Fifth progress payment received (Completion payment)
27 Aug 2014 Independent (PCI) Inspection
28 Aug 2014 Occupancy Permit Received

02 Sep 2014 (Week 35) PCI inspection @7:30am
07 Sep 2014 Picked up Bank Cheque for Builder
10 Sep 2014 (week 36) House cleaned, appliance installed
11 Sep 2014 Final Inspection/Handover (just on 36 weeks build time)

 

 