Sunday 28 September 2014

Front Brick Fence

Sunday 28 Sep 2014

Brick Colour: Austral Chestnut




Fence Footing (500m Deep)









 








 












Brick fence (Steel fence Panel yet to come)



Steel Fence Panels





Front View with Steel Fence Panel Erected - 20 June 2015


Back Yard Concrete

Monday 22 Sep 2014


Colour: Charcoal

Concrete Supplier: Outwest Concrete






Concrete Preparation

 


Concrete Preparation


Concrete Levelling


Concrete Levelling



Concrete Levelled



Day after



Day after


Day after


Friday 12 September 2014

Handover / We Got Keys!! - WK 36

Week 36

Mon 08 Sep - Sun 14 Sep 2014 (Day 183-187)


Final Inspection was booked in for Thursday @ 9:30 am  this week, all paint issues were addressed (The appliance were booked in be delivered and installed a day prior)

Settlement was back at main office in Altona  and was only quick 1/2 an hour


Here are some photos



Kitchen Island - without applicances



Solar Gas Hot Water System



 


Side ColourBond Fence



And finally but not least.................

Keys to our new home



























Saturday 6 September 2014

PCI Done, Settlement BOOKED!! - WK 35

Week 35

Mon 01 Sep - Sun 07 Sep 2014 (Day 178-182)

PCI was booked in for Tuesday @7:30 am  this week. No major issue found just alot of paint touch ups ::lol:: ::lol:: Also the bank valuer were also out to inspect the home on the same day.. How lucky was that?


And Finally but not least.............final inspection /settlement has also been booked in for next Thursday ::cheerleader::


Also received phone call from Bank on Friday to advise everything has been processed and I could go pick up my bank cheque at my nominated bank branch ::cheerleader::::cheerleader::
I am all ready to go, so just a few more sleeps til I get the .   Should be 4pm next Thursday I should have my

Now alot of things to arrange
Concrete
Driveway
Insurance
Curtains
Fence
Telephone connection