11 Sep 2014 Final Inspection/Handover (just on 36 weeks build time)
12 Sep 2014 Security Sliding Doors Fitted (Alfesco, Laundry and balcony Sliding Door) - Invisi-gard
13 Sep 2014 Tile Sealer - Groutpro.com.au


15 Sep 2014 (Week 1) Concrete Preparation
19 Sep 2014 Water Meter Relocation



22 Sep 2014 (Week 2)
  • Concrete Poured (rear and brick fence footing) 
  • Electrical Work (feature lights installed)
  • Telephone connected 

28 Sep 2014 Brick Fence

01 Oct 2014 (Week 3) Side ColourBond Gate
02 Oct 2014 Garden Sheet Roller Door fitted
03 Oct 2014 Brick Fence Acid Cleaned


06 Oct (Week 4)  Front Concrete

13 Oct (Week 5-7) Back yard fill
15 Oct Moved in......................
27 Oct (Week 7) Nature Strip trees planted
08 Nov (Week 8) Garden Shed Complete
20 Nov (Week 10) Front Landscape Complete
27 Nov (Week 11) Pergola Complete 


7 June 2015 (8 Months) Back Yard Landscape Complete -- Artificial Turf installed
20 Jun 2015 (8 Months) Steel Panel Fence Erected
                                  



 

 