Week 7
Mon 17th Feb - Sun 13th Feb2014Ground floor has been wrapped and Brickies has started!!!
Tue 18 Feb - Ground Floor Wrapped - Day 29
Delivery: Laundry Sliding Door Delivered
Today the builders arranged for the ground floor to be wrapped ready for brick work to commence.
Also the SS has arranged for the Alfresco sliding door to be swapped around after I pointed the openings were not as per floor plan.
Before
After
Wed 19 Feb -Bricks Delivered - Day 30
Delivery: Bricks Delivered
Weekly Contract Admin status update:-
' We are just waiting for Brick Layers to become available, also the SS is chasing up for Bricks to be delivered'
Then on the way home I notice the Bricks had been delivered and nicely placed around the house.
Delivery: Bricks Delivered
Weekly Contract Admin status update:-
' We are just waiting for Brick Layers to become available, also the SS is chasing up for Bricks to be delivered'
Then on the way home I notice the Bricks had been delivered and nicely placed around the house.
Thu 20 Feb -Ground Floor Brick Start - Day 31
Today Brickies were on sight and had started bricking to garage side wall and a little to the front door entrance
Today Brickies were on sight and had started bricking to garage side wall and a little to the front door entrance
Fri 21 Feb -Ground Floor Bricking continues - Day 32
Today marks day (2) of Ground Brick work
As the weather was very overcast (chances of showers) this may have set the Brickies back a little as they only managed to finish off the garage side boundary and Rear garage access.
Today marks day (2) of Ground Brick work
As the weather was very overcast (chances of showers) this may have set the Brickies back a little as they only managed to finish off the garage side boundary and Rear garage access.