Watch how a vacant piece of land became our Mentone3850
** NOTE: This page is constantly been updated as we reach a new milestone***
PURCHASE OF LAND - 26 June 2013
This block became ours on 26 June 2013
It is approx 17m by 32m block (620m2), pretty much flat and our neighbouring
blocks have had no rock so decided we go variable site costs because of the condition of our neighbors block (although I was a bit hesitant) so fingers crossed we don't have a massive boulder hiding somewhere in our land! It is titled and ready to go!
|
CUT AND FILL - 09 JAN 2014
(DAY 01) Sight Start
UNDERGROUND PIPES & 35 PIERS - 20 JAN 2014
(DAY 08) Sight Start
SLAB PREPARATION - 22 JAN 2014
(DAY 10) Since Sight Start
SLAB - 23 JAN 2014
(DAY 11) Since Sight Start
GROUND FLOOR FRAMED - 05 FEB 2014
(DAY 20) Since Sight Start
HOUSE FULLY FRAMED & WINDOWS - 12 FEB 2014
(DAY 25) Since Sight Start
GROUND FLOOR BRICKED - 07 MAR 2014
(DAY 42) Since Sight Start
HOUSE FULLY BRICKED - 28 MAR 2014
(DAY 63) Since Sight Start
FACED RENDERING UNDERCOAT - 11 APR 2014
(DAY 69) Since Sight Start
SCAFFOLD DOWN - 01 MAY 2014
(DAY 83) Since Sight Start
GARAGE ROOF & FRONT DOOR- 05 JUNE 2014
(DAY 110) Since Sight Start
GARAGE FACE RENDERING - 13 JUNE 2014
(DAY 115) Since Sight Start
FULL FACE RENDERING - 20 JUNE 2014
(DAY 122) Since Sight Start
GARAGE DOOR PANEL - 04 JULY 2014
(DAY 135) Since Sight Start
TEMP FENCE REMOVE & FRONT DOOR PAINTED - 25 JULY 2014
(DAY 152) Since Sight Start
AT HANDOVER DAY/ Side Shed Frame Erected - 11th Sep 2014
(DAY 186) Since Sight Start
WATER METER REMOVED - 19th Sep 2014
(Week 1) Since Handover Day
BRICK FENCE - 28th Sep 2014
(Week 2) Since Handover Day
FRONT CONCRETE - 6th Oct 2014
(Week 4) Since Handover Day
GARDEN SHED - 8th Nov 2014
(Week 8) Since Handover Day
MENTONE FIRST CHRISTMAS- 26TH Dec 2014
(Week 15) Since Handover Day
FRONT LANDSCAPE- 31st Dec 2014
(Week 16) Since Handover Day
|