Week 6
Mon 10th Feb - Sun 16th Feb2014Builder have been really hard at work this week.. so much has been done
From last week ground floor frames to this week being first floor & garage frames, windows and internal Rough Ins..
Mon 10 Feb -First Floor Frames UP - Day 23
Delivery: Roof Truss and Window Frames
Today marks day (3) of Frame work
The Framer boys were hard at work at 8am because by the time I popped around at 1pm they had packed up and gone home for the day. I guess to make way for delivery of the Roof Truss.
First Floor and Roof Truss delivery
Window Frames in ColourBond - JUNE
Tue 11 Feb - Roof Truss ARE UP - Day 24
Today marks day (4) of Frame work
Was able to catch the Frame boys (there was 4 of them in total) on site and they were kind enough to let me go through to snap some photos
Roof Truss coming up nicely
Today marks day (4) of Frame work
Was able to catch the Frame boys (there was 4 of them in total) on site and they were kind enough to let me go through to snap some photos
Roof Truss coming up nicely
Wed 12 Feb -Garage Frame & Windows - Day 25
Today marks day (5) of Frame work
The Framer were really making up for the lost time during week (4)
They had started and completed the Garage frame and also manage to put up the windows all in one day.. WOW!!
Weekly Contract Admin status update:-
'Framing is near complete.. Once framing work all complete then next is to arrange internal rough ins, wrapping and brick work to start end of next week for the ground floor'
Today marks day (5) of Frame work
The Framer were really making up for the lost time during week (4)
They had started and completed the Garage frame and also manage to put up the windows all in one day.. WOW!!
Weekly Contract Admin status update:-
'Framing is near complete.. Once framing work all complete then next is to arrange internal rough ins, wrapping and brick work to start end of next week for the ground floor'
Here are some photos
Alfresco sliding Doors ( my favor room and windows)
Theatre Room Windows
Do these window look centre to you?
Do these window look centre to you?
Thu 13 Feb -Internal Rough Ins - Day 26
Didn't think there be any work on the house today because Framers pretty much finish (i think) but I wanted to drive by to have a Colourbond (Frame) moment
But to my surprise I then noticed some rubber pipes/hose dangling from the side of the house so thought I pop in and see whats been happening today.. Yap they've started to do the 'Internal Rough Ins'
Here are some photos of the water / gas pipes
Laundry
Gas Meter Pipes
Fri 14 Feb -Internal Rough Ins - Day 27
Frame invoice#
More Internal Rough ins installed
It looks like the plumber came back to finish off the rough ins
Heres some updated photo
Frame invoice#
More Internal Rough ins installed
It looks like the plumber came back to finish off the rough ins
Heres some updated photo
Kitchen Area
Family Area looking towards Meals Area
Laundry Taps
Power Room Taps
Bedroom 1 Ensuite Taps
External Garden Tap
No comments: