Week 9
Mon 03rd Mar - Sun 09 Mar 2014We getting there slowly.. The ground floor after (10) days of Brick work is now 90% complete
Mon 03rd Mar - East Side bricking - Day 38
Ground Floor Brick Work Day 6: Brickies started bricking bottom half of East Side.
Tue 04th Mar - East Side bricking continues - Day 39
Ground Floor Brick Work Day 7: Brickies completed bricking to bottom half of East Side.
Wed 05 Mar - Alfresco Area Bricking - Day 40
Ground Floor Brick Work Day 8: Brickies started bricking near the Alfresco Area.
Weekly Contract Admin status update:-
The bricklayer is due to complete the ground floor brickwork by the end of the week.
SS has now booked in the scaffolding, roof coverings, fascia & guttering & the bricklayer to complete the first floor brickwork.
Thu 06 Mar -- Internal Garage Doors Bricked - Day 41
Delivery: Steel Lintels (Beams)
Ground Floor Brick Work Day 9: As the Steel Lintels beams to above garage Doors and above Alfresco Pillar were delivered today, the brickies were able to complete some more bricking around this area.
Fri 07 Mar - West Side Bricking - Day 42
Delivery: First Floor Bricks
Ground Floor Brick Work Day 10: Brickies were soldering on and completed most of the ground floor brick work to West side.
Also more bricks (To first floor) were delivered today along with a sight clean and sight CAGE emptied out...
Here are some of the finish work to Ground floor to-date..
Not quite there yet but some progress is better than nothing!!!
Front Facade
East Side
Steel Lintels (Beam) above Alfresco Pillar
West Side
Bricking to above Garage Doors Steel beams
House as @ day (42) of Build
** with a sight clean**
** with a sight clean**
I cant wait to next week to hopefully see the Roof tiles go on!!!