Plumbing Fittings - WK 27

Week 27

Mon 07 Jul - Sun  13 Jul 2014 (Day 137 -141)



Besides my house stinking of tobacco & cigarette butts everywhere (thanks to the tradies) we managed to see the plumbing fitting all in and a start of the light fittings (light batten and LED downlights). Also tested the Tap, I have COLD water :: :: :: ::


Work for the week:-
- Ground Floor Tile Grouting (Tuesday)
- Laundry Wall Tiled (Wednesday)
- Plumbing Fittings (Friday)
- Electrical Light Fitting (Friday)


Here are some photos :-

Kitchen Sink Taps



Butler Pantry Sink Taps




Laundry Wall /Floor Tiles




Master Ensuite Basin Taps




Ensuite 2 Basin Taps and Shower fitting
** Also feature wall tiles installed ****


Feature Tile
 Coffee Stone Light (15x100x8mm)

Main Bathroom Basin taps and shower fittings
** Also feature wall tiles installed ****


 




Light Batten and Smoke Alarm



LED downlights to Meal Wall Recess





So maybe by this time next week I can even turn on the light switches, what you reckon?


2 comments:

  1. I would also motivate just about every person to save this web page for any favorite assistance to assist posted the appearance. leak

    ReplyDelete
  2. I learn some new stuff from it too, thanks for sharing your information.
    Küchenarmaturen

    ReplyDelete